  • Broadview Community and Sports Hub – February Update

    We are pleased to announce that the building works have been completed and the builder is finalising defects to the main building. The southern carpark demolition works have commenced with Lead and Asbestos removal which will continue until 9 February. The destructive demolition of the existing building will follow and it's anticipated to be ongoing for 2 weeks. Once the demolition has occurred the site bulk earthworks will follow as part of the carpark construction. The replacement of the oval track is almost finalised with the area being boxed out, imported quarry rubble placed and compacted. These works will be completed by the 9 February and the asphalt placed on the 14 February 2024