March 2018
Initial consultation undertaken to determine the community’s level of support for the Open Space Strategy and any feedback they have.
March 2018
Initial consultation undertaken to determine the community’s level of support for the Open Space Strategy and any feedback they have.
28 October - 21 November 2021
Round 1 consultation on what the community would like to see as part of the upgrade at Peppermint Gums Reserve.
1 February and 5 April 2022
Council Workshops to discuss the outcomes of the Round 1 community consultation and suggestions to prepare a draft concept plan.
February - April 2022
Preparation of a draft concept plan that reflects feedback from the Round 1 community consultation and Council Workshops.
26 April 2022
Council endorsement of the draft concept plan for community consultation (Round 2).
Monday 24 October - Sunday 20 November 2022
Round 2 community consultation on the draft concept plan to refine the plan and ensure it meets community expectations.
October 2023
Finalise the draft concept plan by incorporating the feedback gathered during the Round 2 consultation. Compile the findings and deliver a presentation to the Council, engaging in a discussion regarding the scope and budget.
November/December 2023
Seek endorsement from the Council to advance towards the documentation phase.
January 2024 - June 2024
Pursue various grant funding opportunities to facilitate the successful implementation of the upgrade. The future budget for construction may be considered in the draft budget for the City of Prospect for the 2024/2025 financial year.